Update – [18 August 2026]
As you know, we are seeking to take over management of the estate from the freeholder, Roamquest Ltd (part of the Galliard group; the current managing agent is Galliard Estate Management). Following the membership drive last summer, the company passed the 50% qualifying-leaseholder threshold and served its formal Claim Notice on Roamquest in autumn 2025. The company is represented by solicitors Devonshires, with barrister’s counsel instructed.
The dispute
Roamquest responded with a Counter-Notice dated 12 November 2025 opposing the claim. Having initially raised several objections, the dispute has since narrowed to two main grounds:
1. Whether NCQ is a single “self-contained building” for Right to Manage purposes under the Commonhold and Leasehold Reform Act 2002. The eleven blocks at NCQ sit above one continuous basement/podium car park. Roamquest accepts that the blocks are physically connected but argues that the law does not permit RTM to be exercised across multiple connected blocks — this is now the central legal question in the case.
2. Whether the participation and claim notices were correctly served on every qualifying leaseholder. Because the freeholder did not provide up-to-date leaseholder details, the company relied on Land Registry data to serve every qualifying flat. This point remains in reserve but the company is confident it is defensible.
The court proceedings so far
Because the freeholder did not accept the claim, the company applied to the First-tier Tribunal (Property Chamber) on 7 January 2026. After a period awaiting directions and a hearing date, a first (case management) hearing took place on 31 March 2026. At that hearing the tribunal adjourned the matter to allow both sides to obtain structural expert evidence on the “self-contained building” question.
Directions were then agreed and submitted to the tribunal in mid-May 2026, requiring each party to instruct its own structural expert and to exchange reports. Sourcing a suitably qualified expert took longer than hoped — a number of firms declined the instruction owing to the specialist nature of Right to Manage law and the scale of the development — but an expert was appointed for the RTM company and carried out a site visit at the end of June. The estate’s building history, plans and construction records have been provided to the surveying team.
Where things stand now
The tribunal claim is active and now turns mainly on the “self-contained building” question, with the service point held in reserve. The Experts reports have been completed and filed with the tribunal. No written questions were submitted and the parties now have to file their "Case" with the Tribunal shortly . The Tribunal has set a date early next year for a prelininary hearing on those Case files.
It is worth being realistic about the road ahead. Even if the tribunal accepts that NCQ is a single building, we anticipate that Roamquest may then turn to the second ground and argue that the RTM process itself was not carried out correctly — for example, on the service of notices. In other words, resolving the “single building” question is likely to be an important step rather than the end of the matter, and the proceedings may continue beyond it. Roamquest may also appeal.